jjj

Tuesday 16 February 2016

Obasanjo awarded $841m Abuja rail project without engineering design, MoU- CCECC staff tells Senate panel


An official of the Chinese Civil Engineering and
Construction Company (CCECC) yesterday told a
Senate panel that Former President Olusegun
Obasanjo awarded the $841m Abuja rail project
without engineering design and Memorandum of
Understanding (MoU) in 2007. According to The Guardian Newspaper, CCECC's Project Manager, Etim Abak made the revelation
to the Senate Committee on Federal Capital
Territory (FCT) during an oversight to the project
site. Etim said the then Minister of FCT, Nasir el-
Rufai signed the contract on behalf of the federal
government. The Senate Committee discovered the contract,
which stood at 60.67 kilometres, was inflated by
$10 million (about N2 billion at N200 per dollar)
per kilometre even as the length was later reduced
to 45 kilometres without the refund of the cost for
the 15.67 kilometres dropped. Dino Melaye has demanded the refund of the of $195,878,296.74
( about N392 billion at N200 per dollar) being the
amount for the 15.67 kilometres cut out from the
Chinese Civil Engineering Construction Company
(CCECC), handling the project. The Project Manager of the company, Etim Abak,
while answering questions from members of the
committee, said the contract was signed by the
then FCT minister without design and MOU, saying
it was carried out based on what he simply
identified as a conceptual design. “The contract was awarded based on a
conceptual design and estimates were not
properly done. There was no formal design
submitted and rail bridges and crossover
bridges were not captured in the contract,
“he told the committee. According to him, the contract sum was
$841.645,898 and project completion period was
48 months while the scope of work was 60.67km
standard gauge, with double railway tracks and
associated permanent way within FCT. Melaye
alleged that the project whose length initially stood at 60.67 kilometres, was later reduced to
45.245 without cut in the cost of the project
initially paid for. "Now, you have reduced the length of the
kilometre standard gauge from 60.67 kilometres
to 45.245 kilometres. Meanwhile, there is no
concomitant reduction if you juxtapose the length
of kilometres and the reduction in terms of the
cost. If we are to spend $841 million for 60.67 kilometres and now you have reduced to 45.245
kilometres and the only reduction in terms of
monetary value is from $841.6 million to $823
million and with reduction of just about $17
million dollars, that to me is not commensurate
with the reduction in length. The Federal Government has so far invested $31.5 billion and
another $7.6 billion from the SURE-P fund and if
you put these together, we have $39.1 billion
invested in the rail project, leaving the balance of
$113. 233,155.32million. The sum of $3 billion
dollars was proposed in the 2016 budget of the FCT for the rail project. I did a personal research
and looked at rail construction of the same
specifications , of the same technology across the
globe and one cannot but complain that the cost of
this railway project in Nigeria is on a very high
side.”he said

0 comments:

Post a Comment